Hi KK,
GW#16/17 is currently under large-scale restoration work, including restoration of island and desilting of channel.
Originally, the work is scheduled to be concluded at the end of September. Due to the impact from Typhoon Hato, the work is now scheduled to complete by mid-October.
Vegetation will be treated before the GW being refilled.
Regards,
Katherine Leung
Assistant Reserve Manager
Mai Po Nature Reserve
WWF-HK